Installation & Operation
Figure 1: Example Installation of Sight Glass
An example Sight Glass assembly installation is shown in Figure 1 – on both sides of a Y-Strainer, allowing for a visual inspection of the strainer element. Ideally the Sight Glass assembly is installed in a horizontal position, as shown in Figure 1, or in a vertical (looking down into the sight glass) such that any fluid will be able to be completely drained out of the line. Figure 2 shows an assembled sight glass with tri- clamp.
Figure 2: Assembled VL-3A Sight Glass
DM-0012_VL-3A Sight Glass_IOM_Rev2.0
2 of 4