Mini retractor system TANKO-RF

4. Welding post-treatment

Figure 5.2-3: Grinding

In the interior area, an acid cleaning treatment is recommended after welding. The surface of accessible points can be improved by grinding. The exterior can be treated afterwards by staining, brushing, grinding and polishing. After welding, the container connector can be ground with the interior wall of the container (see Figure 5.2-3: Grinding ).

5.2.3.2 Installation of Clamp PC

A - prozess conection (PA) clamp

B - media connection (MA) clamp

B

A

Figure 5.2-4: Installation of clamp connection

1. Take the container connector out of the packaging and perform a visual inspection for damage. Protect that the O-ring that seals the housing of the TANKO-RF from the container connector from damage. 2. Check the sealing surface in the container connector and on the clamp connections for contamination. Keep the O-ring, O-ring groove and interior surface in the container connector clean. Place the O-ring correctly in the O-ring groove at the bottom end of the housing, if not already pre-assembled. The contact surfaces of the clamp connection between container connector (A, fig. 5.2-4) and housing and on the media connection (B, fig. 5.2-4) must be kept clean.

44/84

Operating/Installation instructions 2023/09

5 Installation

Powered by